- Define configuration parameters
- Implement tagging and identification of components: labyrinths, beam transport, shutter, masks, collimators, and all components that are part of the Radiation Shielding System (RSS).
- Post a list of RSS devices in the display case, known as the Configuration Control Component List (CCCL).
- Understand CCWP Procedure
- Propose or accept CCWP requests
- Understand the conditions of the work permit.
- Obtain or verify the approval authority required.
- Follow up on work being done, follow larger projects from start to end as Project Coordinator.
- Close out the CCWP, obtain close out approvals if needed.
- Arrange for HP type C survey if needed.
- Give Global Online and APS enable.
|
|
- Evaluate and approve beamline readiness.
- Initiate APS Enable allowing beam into the beamline.
|
|
- Understand the posting requirements and responsibilities for a beamline:CAA/BOA/ESAF, Configuration Control Work Permit (yellow sheet), Shutter Authorization (green sheet), Administrative restriction (pink sheet), CCCL/RSS devices list.
- Enter correct date/time data for the start/end of experiments, especially proprietary experiments, in the online ESAF entry form.
|
|
- Putting a beamline Global Online
- Understand Global Online/Offline Procedure
- Approvals:PSS system manager, ACIS system manager, Floor Coordinator
- Taking a Beamline Offline
- Understand Global On Line/Off Line Procedure
- Approvals:Floor Coordinator
|
|
- Set up beam scatter devices, ozone equipment, and flight tubes.
- Measure beamstops using Ray Trace information.
- Assist in arranging for BCRRT, Beamline Commissioning Readiness Review.
- Prepare beamline configuration controls:Configuration Control Components List (CCCL), RSS tagging of components
- Post commissioning documents, Commissioning Activity Approval (CAA) form or ESAF.
- Assist Configuration Control System Manager (CCSM), Radiation Safety Officer (RSO), and Health Physics (HP) technicians: participation and oversight.
- Help to set up verification hardware and equipment.
- Verify FE-EPS readiness. Help Beamline Personnel with BL-EPS readiness.
- Verify ID positioning if shielding verification is done on an ID beamline.
- Provide Global Online.
- Administer APS Enable.
|
|
- File trouble report for recurring or unusual warnings, trips, or faults, or any faults that require investigation.
- Follow up on actions related to the trouble report.
|
|
- Know and understand which users need to be called for each situation.
- Know when and how to call support personnel, HP system specialists, and emergency personnel.
|
|
- Understand how to access current beam position information.
- Understand how to compare current to past beam position data.
- Understand policy on steering limits.
- Understand how beamline personnel may issue their own orbit corrections using EPICS.
- Initiate orbit corrections using the APS Steering Request Webpage or verbally with the Control Room operators.
|
|