Note: Electrical service interruption to the APS is NOT expected as a result of this project. Phase 1: Meade has confirmed that they are on schedule to complete bus 1 replacement at 549 during the spring APS shutdown, specifically April 24-May 8, with clean power to APS by May 13. Phase 2: Meade will also complete the 549 bus 2 replacement during the APS fall shutdown, specifically August 22-September 12, with clean power to APS by September 16. |
Status |
-/- |