CAT Chat Minutes

January 20, 2003

 

Information and Follow-up

There is a need for cryo-pumps to be serviced in a timely fashion. ME group appears to be meeting the need. If there is a problem, contact the floor coordinators.

A decision on whether the fourth of July scheduling should be changed is forthcoming.

 

Operations

Operation Stats: Glenn Decker reported that the next scheduled run begins January 29th at 0800 hours in non top-up operation. Regarding future scheduling, a suggestion was made to move Fall shutdown up by one week. The APS FY2003 Schedule beginning in June will be published after approval by J. M. Gibson.

LOM Access: Automated time control of LOM interior sliding doors is progressing and should be operable by the end of this week. LOM truck lock doors are presently auto time controlled to NOT require card key during the hours of 6:00 a.m. to 7:00 p.m., Monday through Friday. Use of the card key outside of these times as well as on holidays and weekends will be necessary.