27-ID and 35-ID, Construction Schedule

This is a tentative schedule of the daily construction at 27-ID and 35-ID. For the preliminary two to three week look ahead schedule, please click the PDF calendar to the left. The potential for ground vibration is noted in the "Impact" column (None, Small, Moderate, High, Very High).

05.13.2013 - 06.03.2013

Day
Activity Impact
Week of 05.13.13
completion of 35-ID-B roof panels, installation of lead trim, steel capping and door installation. Low
Week of 05.20.13
35-ID-C panels arrive begin installation of 35-ID-C wall and roof panels Low
Week of 06.03.13
continue installation of 35-ID-C panels, doors, roof and floor trim Low

Since these are studies days, the impact on users should be low, but there will be vibration that could affect the storage ring.
The above dates are tentative and are subject to change depending on weather, equipment problems, delivery issues, need for rework to meet specifications, interfering factors, etc. The uncertainty in the dates of these activities increases for farther away days, please check daily for the best updates. Column Line Numbers are posted at each steel column in the Experiment Hall.