27-ID and 35-ID Past Construction

Past 27-ID and 35-ID Construction

Day
Activity Impact
Week of 06.11.13
35-ID-D panels arrive, 35-ID-C panel installation complete. Start installation of 35-ID-D. -/-
Week of 06.13.13
DCS/RIXS Construction Progress Meeting, LOM 438-C010, 9AM -/-
Week of 06.18.13
27-ID-A panels arrive -/-
Week of 06.25.13
first shipment of 35-ID-E panels arrives -/-
Week of 06.03.13
continue installation of 35-ID-C panels, doors, roof and floor trim Low
Week of 05.20.13
35-ID-C panels arrive begin installation of 35-ID-C wall and roof panels Low
Week of 05.13.13
completion of 35-ID-B roof panels, installation of lead trim, steel capping and door installation. Low
Tuesday - 03.05.13
Cutting floor trough for 35-ID-B Medium
Tuesday - 03.11.13
Cutting floor trough for 35-ID-C Medium
Tuesday - 03.12.13
Cutting floor trough for 35-ID-C Medium
Tuesday - 03.19.13
Cutting floor trough for 35-ID-C Medium
Tuesday - 03.26.13
Cutting floor trough for 35-ID-C (Tentative) Medium
Monday - 02.25.13
Cutting floor trough for 35-ID-B Medium
Tuesday - 02.26.13
Cutting floor trough for 35-ID-B Medium