| Monday - 04.02.2012 |
| Layout & Survey |
None |
| Concrete & Soil Testing |
None |
| Caisson Drilling and concrete pours |
small |
|
| Tuesday - 04.03.2012 |
| Layout & Survey |
None |
| Concrete & Soil Testing |
None |
| Caisson Drilling and concrete pours |
small |
| Underground Plumbing, trenching and laying pipes |
Moderate |
| Excavation and back-fill between columns 78 to 80, vibratory roller compactor |
Very High |
|
| Wednesday - 04.04.2012 |
| Layout & Survey |
None |
| Concrete & Soil Testing |
None |
| Caisson drilling and concrete pours |
small |
|
| Thursday - 04.05.2012 |
| Layout & Survey |
None |
| Excavate for Foundation (Canceled) |
Moderate |
|
| Friday - 04.06.2012 |
| Layout & Survey |
None |
| Underground Plumbing, trenching and laying pipes |
Moderate |
| Excavation and Concrete for Foundation |
Moderate |
|
| Saturday - 04.07.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 04.08.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 04.09.2012 |
| Layout & Survey |
None |
| Underground Plumbing, trenching and laying pipes |
Small |
| Forms and Rebar for Concrete for Foundation (Columns 72 to 77) |
Small |
|
| Tuesday - 04.10.2012 |
| Layout & Survey |
None |
| Underground Plumbing, trenching and laying pipes, and Backfilling |
Small |
| Forms and Rebar for Concrete for Foundation (Columns 72 to 77) |
Small |
|
| Wednesday - 04.11.2012 |
| Layout & Survey |
None |
| Underground Plumbing, trenching and laying pipes |
Small |
| Electric Grounding |
Small |
| Forms and Rebar for Concrete for Foundation (Columns 72 to 77) |
Small |
|
| Thursday - 04.12.2012 |
| Layout & Survey |
None |
| Concrete & Soil Testing |
None |
| Underground Plumbing, trenching and laying pipes |
Small |
| Electric Grounding |
Small |
| Forms and Rebar for Concrete for Foundation (Columns 72 to 77) |
Small |
|
| Friday - 04.13.2012 |
| Layout & Survey |
None |
| Concrete & Soil Testing |
None |
| Underground Plumbing, trenching and laying pipes, and Backfilling |
Small |
| Electric Grounding |
Small |
| Pour Concrete for Foundation (Columns 72 to 77) |
Moderate |
|
| Saturday - 04.14.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 04.15.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 04.16.2012 |
| Layout & Survey |
None |
| Concrete & Soil testing |
None |
| Forms and Rebar for Concrete for Foundation (Columns 79 to 80) |
Small |
| Strip Concrete, Backfill & Compaction |
Moderate |
|
| Tuesday - 04.17.2012 |
| Layout & Survey |
None |
| Concrete & Soil testing |
None |
| Underground Plumbing, trenching and laying pipes, and Backfilling |
Small |
| Forms and Rebar for Concrete for Foundation (Columns 79 to 80) |
Small |
| Backfill & Compaction |
Moderate |
| Major Compaction with Vibratory Roller |
Very high |
|
| Wednesday - 04.18.2012 |
| Layout & Survey |
None |
| Concrete & Soil testing |
None |
| Underground Plumbing, trenching and laying pipes, and Backfilling |
Small |
| Backfill & Compaction |
Moderate |
| 6' Test Well Drilling? |
Moderate |
| Forms and Rebar for Concrete for Foundation (Columns 79 to 80) |
Moderate |
|
| Thursday - 04.19.2012 |
| Layout & Survey |
None |
| Concrete & Soil Testing |
None |
| Underground Plumbing, trenching and laying pipes, and Backfilling |
Small |
| Pour Concrete for Foundation (Columns 79 to 80) |
Moderate |
|
| Friday - 04.20.2012 |
| Layout & Survey |
None |
| Concrete & Soil Testing |
None |
| Underground Plumbing, trenching and laying pipes |
Small |
| Strip Concrete Forms |
Small |
|
| Saturday - 04.21.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 04.22.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 04.23.2012 |
| Layout & Survey |
None |
| Underground Plumbing, trenching and laying pipes |
Small |
| Backfill & Compaction |
Moderate |
|
| Tuesday - 04.24.2012 |
| Layout & Survey |
None |
| Underground Plumbing, trenching and laying pipes (Erroneously labeled as Very High) |
Small |
| Backfill & Compaction |
Moderate |
|
| Wednesday - 04.25.2012 |
| Layout & Survey |
None |
| Underground Plumbing, trenching and laying pipes |
Small |
| Backfill & Compaction |
Moderate |
|
| APS Shutdown |
|
| Thursday - 04.26.2012 |
| Layout & Survey |
None |
| Concrete & Soil Testing |
None |
| Underground Plumbing, trenching and laying pipes |
Small |
| Utility Runs in Experimental Hall Aisle |
Small |
|
| Friday - 04.27.2012 |
| Layout & Survey |
None |
| Underground Plumbing, trenching and laying pipes |
Small |
| Utility Runs in Experimental Hall Aisle |
Small |
|
| Saturday - 04.28.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 04.29.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 04.30.2012 |
| Utility Runs in Experimental Hall |
Small |
| Underground Plumbing, trenching and laying pipes |
Small |
|
| Tuesday - 05.01.2012 |
| Utility Runs in Experimental Hall |
Small |
| Underground Plumbing, trenching and laying pipes |
Small |
|
| Wednesday - 05.02.2012 |
| Utility Runs in Experimental Hall |
Small |
| Underground Plumbing, trenching and laying pipes |
Small |
|
| Thursday - 05.03.2012 |
| Utility Runs in Experimental Hall |
Small |
| Underground Plumbing, trenching and laying pipes |
Small |
|
| Friday - 05.04.2012 |
| Utility Runs in Experimental Hall |
Small |
| Underground Plumbing, trenching and laying pipes |
Small |
| Preparation for Floor Slab |
Moderate |
|
| Saturday - 05.05.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 05.06.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 05.07.2012 |
| Utility Runs in Experimental Hall |
Small |
| Preparation for Floor Slab (Plumbing & Grounding) |
Moderate |
|
| Tuesday - 05.08.2012 |
| Layout & Testing |
None |
| Utility Runs in Experimental Hall |
Small |
| Preparation for Floor Slab (Plumbing & Grounding) |
Moderate |
| Backfill and Compaction |
Moderate |
|
| Wednesday - 05.09.2012 |
| Utility Runs in Experimental Hall |
Small |
| Layout & Testing |
None |
| Backfill and Compaction |
Moderate |
| Preparation for Floor Slab (Plumbing) |
Moderate |
|
| Thursday - 05.10.2012 |
| Layout & Testing |
None |
| Utility Runs in Experimental Hall |
Small |
| Reinforcements for Slab |
Small |
| Backfill and Compaction |
Moderate |
|
| Friday - 05.11.2012 |
| Layout & Testing |
None |
| Utility Runs in Experimental Hall |
Small |
| Backfill and Compaction |
Moderate |
|
| Saturday - 05.12.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 05.13.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 05.14.2012 |
| Layout & Testing |
None |
| Utility Runs in Experimental Hall |
Small |
| Preparation for Floor Slab |
Small |
|
| Tuesday - 05.15.2012 |
| Utility Runs in Experimental Hall |
Small |
| Formwork for Floor Slab |
Moderate |
|
| Wednesday - 05.16.2012 |
| Layout & Testing |
None |
| Utility Runs in Experimental Hall |
Small |
| Reinforcements for Floor Slab |
Small |
|
| Thursday - 05.17.2012 |
| Layout & Testing |
None |
| Utility Runs in Experimental Hall |
Small |
| Reinforcements for Floor Slab |
Small |
|
| Friday - 05.18.2012 |
| Saw Cut Slab Joints |
Small |
| Utility Runs in Experimental Hall |
Small |
| Pour Floor Slab |
Moderate |
|
| Saturday - 05.19.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 05.20.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 05.21.2012 |
| Layout & Testing |
None |
| Utility Runs in Experimental Hall |
Small |
| Strip Forms & Cleanup |
Small |
|
| Tuesday - 05.22.2012 |
| Utility Runs in Experimental Hall |
Small |
|
| Wednesday - 05.23.2012 |
| Layout & Testing |
None |
| Utility Runs in Experimental Hall |
Small |
| Preparation for Steel Installation |
Small |
|
| Thursday - 05.24.2012 |
| Layout & Testing |
None |
| Utility Runs in Experimental Hall |
Small |
| Structural Steel Installation (Columns 72 to 75) |
Moderate |
|
| Friday - 05.25.2012 |
| Layout & Testing |
None |
| Utility Runs in Experimental Hall |
Small |
| Structural Steel Installation (Columns 72 to 75) |
Moderate |
|
| Saturday - 05.26.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 05.27.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 05.28.2012 |
|
| Tuesday - 05.29.2012 |
| Layout & Testing |
None |
| Structural Steel Installation (Columns 72 to 75) |
Moderate |
|
| Wednesday - 05.30.2012 |
| Layout & Testing |
None |
| Cable Pull on S.R. Mezzanine |
Small |
| Structural Steel Installation (Columns 72 to 75) |
Moderate |
|
| Thursday - 05.31.2012 |
| Layout & Testing |
None |
| Structural Steel Installation (Columns 72 to 75) |
Moderate |
|
| Friday - 06.01.2012 |
| Layout & Testing |
None |
| Structural Steel Installation (Columns 72 to 75) |
Moderate |
|
| Saturday - 06.02.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 06.03.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 06.04.2012 |
| Paint Steel |
Small |
| Pipes & Sprinklers |
Small |
| Structural Steel Installation (Columns 72 to 75) |
Moderate |
|
| Tuesday - 06.05.2012 |
| Paint Steel |
Small |
| Electrical |
Small |
| Structural Steel Installation (Columns 72 to 75) |
Moderate |
|
| Wednesday - 06.06.2012 |
| Layout & Testing |
None |
| Paint Steel |
Small |
| Structural Steel Installation (Columns 72 to 75) |
Moderate |
| Carpentry, Roof Blocking |
Moderate |
|
| Thursday - 06.07.2012 |
| Layout & Testing |
None |
| Paint Steel |
Small |
| Pipes & Sprinklers |
Small |
| Carpentry, Roof Blocking |
Moderate |
|
| Friday - 06.08.2012 |
| Layout & Testing |
None |
| Roofing |
Small |
| Pipes & Sprinklers |
Small |
| Paint Steel |
Small |
| Carpentry, Roof Blocking |
Moderate |
|
| Saturday - 06.09.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 06.10.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 06.11.2012 |
| Paint Steel |
Small |
| Roofing |
Small |
| Pipes & Sprinklers |
Small |
|
| Tuesday - 06.12.2012 |
| Paint Steel |
Small |
| Roofing |
Small |
|
| Wednesday - 06.13.2012 |
| Paint Steel |
Small |
| Roofing |
Small |
| Pipes & Sprinklers |
Small |
| Structural Steel Installation (Columns 72 to 75) |
Moderate |
|
| Thursday - 06.14.2012 |
| Roofing |
Small |
| Pipes & Sprinklers |
Small |
| Siding Installation |
Moderate |
| Structural Steel Installation (Columns 72 to 75) |
Moderate |
|
| Friday - 06.15.2012 |
| Layout & Testing |
None |
| Roofing |
Small |
| Pipes & Sprinklers |
Small |
| Siding Installation |
Moderate |
|
| Saturday - 06.16.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 06.17.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 06.18.2012 |
| Plumbing |
Small |
| Electrical |
Small |
| Siding Installation |
Moderate |
|
| Tuesday - 06.19.2012 |
| Electrical |
Small |
| Plumbing |
Small |
|
| Wednesday - 06.20.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Plumbing |
Small |
| Siding Installation |
Moderate |
|
| Thursday - 06.21.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Plumbing |
Small |
| Siding Installation |
Moderate |
|
| Friday - 06.22.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Plumbing |
Small |
| Siding Installation |
Moderate |
|
| Saturday - 06.23.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 06.24.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 06.25.2012 |
| No On-Site Construction, Waiting For Phase 2 Steel. |
None |
|
| Tuesday - 06.26.2012 |
| No On-Site Construction, Waiting For Phase 2 Steel. |
None |
|
| Wednesday - 06.27.2012 |
| No On-Site Construction, Waiting For Phase 2 Steel. |
None |
|
| Thursday - 06.28.2012 |
| No On-Site Construction, Waiting For Phase 2 Steel. |
None |
|
| Friday - 06.29.2012 |
| No On-Site Construction, Waiting For Phase 2 Steel. |
None |
|
| Saturday - 06.30.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 07.01.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 07.02.2012 |
| Electrical |
Small |
| Framing Bathroom |
Small |
| Plumbing (Test Wells) |
Moderate |
|
| Tuesday - 07.03.2012 |
| HVAC |
Small |
| Electrical |
Small |
|
| Wednesday - 07.04.2012 |
|
| Thursday - 07.05.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Framing Bathroom |
Small |
|
| Friday - 07.06.2012 |
| HVAC |
Small |
| Electrical |
Small |
|
| Saturday - 07.07.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 07.08.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 07.09.2012 |
| HVAC |
Small |
| Electrical |
Small |
|
| Tuesday - 07.10.2012 |
| HVAC |
Small |
| Electrical |
Small |
|
| Wednesday - 07.11.2012 |
| HVAC |
Small |
| Electrical |
Small |
|
| Thursday - 07.12.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Framing Bathroom |
Small |
|
| Friday - 07.13.2012 |
| HVAC |
Small |
| Electrical |
Small |
|
| Saturday - 07.14.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 07.15.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 07.16.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Structural Steel Phase 2 |
Moderate |
|
| Tuesday - 07.17.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Structural Steel Phase 2 |
Moderate |
|
| Wednesday - 07.18.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Structural Steel Phase 2 |
Moderate |
|
| Thursday - 07.19.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Structural Steel Phase 2 |
Moderate |
|
| Friday - 07.20.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Structural Steel Phase 2 |
Moderate |
|
| Saturday - 07.21.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 07.22.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 07.23.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Structural Steel Phase 2 |
Moderate |
| Test Well Installation |
Moderate |
|
| Tuesday - 07.24.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Structural Steel Phase 2 |
Moderate |
| Test Well Installation |
Moderate |
|
| Wednesday - 07.25.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Structural Steel Phase 2 |
Moderate |
| Test Well Installation |
Moderate |
|
| Thursday - 07.26.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Paint |
Small |
| Misc. Concrete Pours |
Small |
| Structural Steel Phase 2 |
Moderate |
| Test Well Installation |
Moderate |
|
| Friday - 07.27.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Paint |
Small |
| Misc. Concrete Pours |
Small |
| Structural Steel Phase 2 |
Moderate |
| Test Well Installation |
Moderate |
|
| Saturday - 07.28.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 07.29.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 07.30.2012 |
| Electrical |
Small |
| Paint |
Small |
| Structural Steel Phase 2 |
Moderate |
| Work Inside Existing 400A Building |
Moderate |
|
| Tuesday - 07.31.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Paint |
Small |
| Structural Steel Phase 2 |
Moderate |
| Work Inside Existing 400A Building |
Moderate |
|
| Wednesday - 08.01.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Paint |
Small |
| Misc. Concrete Pours |
Small |
| Structural Steel Phase 2 |
Moderate |
| Work Inside Existing 400A Building |
Moderate |
|
| Thursday - 08.02.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Paint |
Small |
| Misc. Concrete Pours |
Small |
| Sprinkler |
Small |
| Structural Steel Phase 2 |
Moderate |
| Work Inside Existing 400A Building |
Moderate |
|
| Friday - 08.03.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Paint |
Small |
| Misc. Concrete Pours |
Small |
| Sprinkler |
Small |
| Structural Steel Phase 2 |
Moderate |
| Work Inside Existing 400A Building |
Moderate |
|
| Saturday - 08.04.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 08.05.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 08.06.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Paint |
Small |
| Sprinkler |
Small |
| Siding |
Small |
| Roofing |
Small |
| Structural Steel Phase 2 |
Moderate |
| Work Inside Existing 400A Building |
Moderate |
|
| Tuesday - 08.07.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Paint |
Small |
| Sprinkler |
Small |
| Siding |
Small |
| Roofing |
Small |
| Work Inside Existing 400A Building |
Moderate |
|
| Wednesday - 08.08.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Paint |
Small |
| Sprinkler |
Small |
| Siding |
Small |
| Roofing |
Small |
| Work Inside Existing 400A Building |
Moderate |
|
| Thursday - 08.09.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Paint |
Small |
| Sprinkler |
Small |
| Siding |
Small |
| Roofing |
Small |
| Work Inside Existing 400A Building |
Moderate |
|
| Friday - 08.10.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Paint |
Small |
| Sprinkler |
Small |
| Siding |
Small |
| Roofing |
Small |
| Work Inside Existing 400A Building |
Moderate |
|
| Saturday - 08.11.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 08.12.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 08.13.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Paint |
Small |
| Plumbing |
Small |
| Carpentry |
Small |
| Siding |
Small |
| Sprinkler |
Small |
|
| Tuesday - 08.14.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Plumbing |
Small |
| Carpentry |
Small |
| Siding |
Small |
| Sprinkler |
Small |
|
| Wednesday - 08.15.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Plumbing |
Small |
| Carpentry |
Small |
| Siding |
Small |
| Sprinkler |
Small |
|
| Thursday - 08.16.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Plumbing |
Small |
| Carpentry |
Small |
| Siding |
Small |
|
| Friday - 08.17.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Plumbing |
Small |
| Carpentry |
Small |
| Siding |
Small |
|
| Saturday - 08.18.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 08.19.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 08.20.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Siding |
Small |
| Roofing |
Small |
| Site Finish Grading |
Moderate |
|
| Tuesday - 08.21.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Siding |
Small |
| Roofing |
Small |
| Site Finish Grading |
Moderate |
|
| Wednesday - 08.22.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Roofing |
Small |
| Site Finish Grading |
Moderate |
|
| Thursday - 08.23.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Roofing |
Small |
| Site Finish Grading |
Moderate |
|
| Friday - 08.24.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Roofing |
Small |
| Site Finish Grading |
Moderate |
|
| Saturday - 08.25.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 08.26.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 08.27.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Carpentry & Painting |
Small |
| Site Work & Landscaping |
Small |
|
| Tuesday - 08.28.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Carpentry & Painting |
Small |
| Site Work & Landscaping |
Small |
|
| Wednesday - 08.29.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Carpentry & Painting |
Small |
| Site Work & Landscaping |
Small |
|
| Thursday - 08.30.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Carpentry & Painting |
Small |
| Site Work & Landscaping |
Small |
|
| Friday - 08.31.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Carpentry & Painting |
Small |
| Site Work & Landscaping |
Small |
|
| Saturday - 09.01.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 09.02.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Monday - 09.03.2012 |
|
| Tuesday - 09.04.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Carpentry & Painting |
Small |
| Site Work & Landscaping |
Small |
|
| Wednesday - 09.05.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Carpentry & Painting |
Small |
| Site Work & Landscaping |
Small |
|
| Thursday - 09.06.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Carpentry & Painting |
Small |
| Site Work & Landscaping |
Small |
|
| Friday - 09.07.2012 |
| HVAC |
Small |
| Electrical |
Small |
| Carpentry & Painting |
Small |
| Site Work & Landscaping |
Small |
|
| Saturday - 09.08.2012 |
| No work is scheduled for the weekends |
-/- |
|
| Sunday - 09.09.2012 |
| No work is scheduled for the weekends |
-/- |
|